Frontier Pkwy

Frontier Parkway will transform from a two-lane blacktop to a divided, four-lane, concrete thoroughfare which includes a bridge overpassing the BNSF tracks. Frontier Parkway will become one of the area’s major east-west connector routes.

Preston To Dallas North Tollway 

  • Start: February 2021
  • Finish: 2023

Custer to Preston (FM1461)

  • Start: 2024
  • Finish: 2026

Dallas North Tollway to FM1385

  • Start: 2020
  • Finish: 2026

Frontier Pkwy Project will be built in four different phases. Please see below for more information on the project!

Frontier Pkwy Project Schematic

Phase 1

Phase 2

Phase 3

Phase 4

Construction Start - March 2021

Construction Substantially Complete - December 2022

Contractor: Mario Sinacola & Sons Excavating Inc

Cost $22 Million

NCTCOG Exhibit